We used necessary cookies for the website to function correctly, guaranteeing basic functionalities and the security of the website. In addition. Depending on your selection, we will use our own and third-party cookies to improve the functioning; preferences cookies, related to the type of browser or the region from which you access, and/or marketing cookies that allow us to analyze browsing habits. For further information, please consult our cookies policyopens in a new tab.

You can accept all cookies, configure them or reject their use bellow.

Our foundation: acciona.org Initiatives we support Our strategy Sustainable Development Goals Social development Sustainability indices Sustainable Development Alliances Technology and innovation centres Open and collaborative innovation Digital hub Innovation projects Job offers Graduates and internships Opportunities and inclusion Safety, health and well-being Training Energy Transport Water Social Cities Real Estate Financial Integrated annual report Annual accounts Results, reports & presentations Average period of payment to suppliers Ratings Share price Dividends Analyst opinions Investor calendar General Shareholders' Meeting Board of Directors and Committees Share capital Annual Corporate Governance Report Director remuneration Governance rules and compliance Framework Agreement CNMV Communications Sustainable finance
Transport
28 OCT 2026
  • The transmission line is one of the country's largest energy infrastructure initiatives

ACCIONA, together with its local partner Genus, has begun using helicopters to string conductors on the HumeLink East transmission line in Australia.

The transmission line is one of the country's largest energy infrastructure initiatives. The project involves the design and construction of 225 kilometers of 500 kV overhead transmission lines from Bannaby to Wondalga, as well as the upgrade of the 500 kV Bannaby substation.

The contract, awarded by Australian company Transgrid, also includes the construction of 459 transmission towers that support more than 6,000 kilometers of conductor. The project's main objective is to reshape the region's electricity market, strengthen grid stability and facilitate the transition to new renewable energy sources.

At HumeLink East, ACCIONA is using helicopters for conductor stringing, a safer and faster method. This method also has less impact on landowners and local communities than traditional ground-based methods, which involve using excavators and other ground equipment between transmission towers.

Construction continues to advance through the use of new techniques. The project is creating more than 1,600 jobs throughout its construction phases. The first transmission tower was erected in January 2026, followed by the 100th tower in July 2026. Once completed, the transmission line will help provide a more affordable, reliable and sustainable electricity supply by increasing the capacity to deliver clean energy to millions of consumers.