11km

of highway

We guarantee safe and efficient movement

Concession for the design, construction, financing, operation and maintenance of a new 11 km highway that linked the 407 of Ontario (Canada) with the I-75 in Michigan (USA), consisted of three lanes in each direction, of which 8 km passed through a clearing site and the other three were built using the cut and fill process.

It consisted of an innovative 6-lane, 11-kilometre highway that offered benefits for transport, green spaces, recreational trails and community connections.

 

Traffic management during construction and phase scheduling had been of great importance due to the need to maintain traffic along the existing highway, Highway 3, which will be progressively diverted to allow for the construction of the main highway, Highway 401.

 

The project included the construction of the new bridge that will replace the current one, as well as the execution of road connections in its two distribution hubs to guarantee the fluidity of traffic between New Westminster and Surrey.

 

The new bridge conssited of four lanes (two in each direction) for cars and commercial vehicles, separated by a central reservation.

Completion of the new bridge is scheduled for 2023. Once in operation, the new Pattullo Bridge will improve traffic safety for cars, cyclists and pedestrians. The current Pattullo bridge will be removed as part of the project.

 

The new section included a train underpass and a new interchange at Warrell Creek. In total, the project included the construction of 15 bridges, notably the 850-metre bridge crossing the Nambucca River, two new interchanges and access ramps to North Macksville.

 

The construction also included the supply and installation of electromechanical equipment, advanced traffic management system (ATMS) and traffic signals for the project, including related civil works. The works carried out for the ATMS installation included the implementation of variable message signalling systems (VMS) and (AAS), closed circuit television cameras (CCTV) and everything that makes up the infrastructure of a communication network, as well as, fibre optics throughout the motorway development.

 

As one of the leading organisations that continually pursues corporate social responsibility strategies at the core of our business, ACCIONA stands out among our peers as a company with superior operational efficiency, climate change strategy, supplier control standards, workplace health and safety policies, and our management code of conduct and ethical practices.

 

COMMUNITY BENEFITS

  • The Parkway enables the safe and efficient movement of people, goods and services along route 401.
  • Separats local and international traffic.
  • It has eliminated intermittent traffic in residential areas along its route.
  • In the near future, the Parkway will connect the 401 directly to a new Canadian inspection site and the Gordie Howe International Bridge.

GENERAL INFORMATION

  • Location: Windsor, Ontario, Canada.
  • Contract type: Design, construction, financing, operation and maintenance (PPP) for a 30 year period.
  • Infrastructure: An 11 km highway consisted of three lanes in each direction, plus a 2+2 road that intersected with the main road and served the adjoining streets. The project consisted of 12 cut-and-cover tunnels, 12 overpasses, 34 km² of retaining walls and 41 km² of acoustic screens.
  • Year of project completion: 2015

KEY ASPECTS

This was the largest investment in history for a highway project in the Canadian province of Ontario.

The Rt. Hon. Herb Gray Parkway included three essential components:

  • A six-lane extension of Highway 401 that stretched below the level from the area west of the North Talbot Road Bridge to EC Row Expressway, and then parallel to EC Row Expressway until Ojibway Parkway.
  • A four-lane extension of Highway 3 that included the multi-lane roundabout towards the EC Row Highway area, where was joined Huron Church Road.
  • The Parkway Trail, which spaned approximately 17 kilometres, was located within 120 hectares (300 acres) of green space adjacent to the two stretches of roads and through the 11 peaks of the tunnel.

Key figures

6,917,756

m3 of excavation

78,734

m3 of concrete for pavement

292,636

tonnes of tarmac mix

32,000

linear metres of concrete barriers

38,893

linear metres of prefabricated beams

105,000

m3 of structural concrete

17,850

tonnes of reinforcement frames

430,648

linear metres of electricity cables

34,407

linear metres of optical fibre

Our environmental impact

Technology and innovation

A complete communication system and fibre optics

Construction included the supply and installation of electromechanical equipment, the Advanced Traffic Management System (ATMS) and traffic signals for the project, including the related civil works.

The works carried out for the ATMS installation included the implementation of systems for variable message signs (VMS and AAS), closed circuit television cameras (CCTV) and everything that makes up the infrastructure of a communication network, as well as the fibre optics throughout the development of the highway.

    Other projects of ACCIONA

    All of our projects