CLEAN, NON-POLLUTING ENERGY
Ensure access to affordable, reliable, sustainable and modern energy for all
1 in 8 people still do not have access to electricity. In order to ensure access to affordable, reliable, sustainable and modern energy for all, it is necessary to increase the use of renewable energy from 25 % today to 38 % in 2025.
ACCIONA is positioning itself as a key player in addressing the growth in energy demand while curbing the progress of global warming and promoting the transition to a decarbonized energy model.
CLIMATE ACTION
Take urgent action to combat climate change and its impacts
The generation and use of energy is responsible for 74 % of total greenhouse gas emissions in the world. This activity is the largest contributor to global warming. Investment in renewable energy, energy efficiency and other low carbon technologies will continue to be essential to meet the new needs of humanity and to minimise their negative impact on the environment.
ACCIONA considers the fight against climate change and its related effects to be a strategic priority. The Company is working to mitigate greenhouse gas emissions in order to contribute to the progress of society and respond to the main challenges of sustainable development in the areas of infrastructure, water and energy, leading the transition to a low-carbon economy.
Fort Bend Solar Farm represents an estimated $258 million investment and would employ up to 450 people at peak construction. It would create 12 full-time jobs during operation.
ACCIONA Energía's team is committed to using local businesses and services providers when possible during construction and operation.
Local Benefits of Solar Energy
- A boost in tax revenue without an increased demand on local services like police and schools
- Local job creation and support of local businesses
- Local partnership opportunities. Each ACCIONA Energía project includes a social impact management program dedicated to advancing education, wellness or environmental stewardship
GENERAL INFORMATION
- Location: Fort Bend County, Texas
- Capacity: 240 MW PV
- Technology: Solar panels affixed to solar trackers
- Timeline:
- Local Permitting: 2021
- Construction: 2021-2023
- Begin Operations: 2023
- Owners: ACCIONA Energía
KEY POINTS
- ACCIONA Energía’s fourth renewable energy project in Texas, joining three wind farms in Cameron County.
- Key project in a portfolio of solar farms being developed by ACCIONA Energía to deliver more than a gigawatt of new solar by the end of 2023
- Site will feature solar panels, affixed to solar trackers that maximize production throughout the day.
- Up to 450 new direct jobs during peak construction and 12 permanent jobs once operational