Our foundation: acciona.org Initiatives we support Our strategy Sustainable Development Goals Climate emergency Social development Sustainability indices Sustainable Development Alliances Technology and innovation centres Open and collaborative innovation Digital hub Innovation projects Job offers Graduates and internships Diversity, equity and inclusion Safety, health and well-being Training Selection process Energy Transport Water Social Cities Real Estate Financial Integrated annual reports Annual accounts Results, reports & presentations Average period of payment to suppliers Ratings Share price Dividends Analyst opinions Investor calendar General Shareholders' Meeting Board of Directors and Committees Management team Share capital Annual Corporate Governance Report Director remuneration Governance rules and compliance Framework Agreement CNMV Communications Sustainable finance
New port area Murcia, Spain See on Google Maps
This project involved the construction of the breakwater and the jetty that make up the new port area on the Mediterranean side.

The project included the construction of a 606.8-m long enclosure dike between Punta de los Aguilones and the Escombreras islet that surrounds it, a 580.6-m long perimeter dike and a jetty parallel to the existing Bastarreche dike, thus creating a 70 hectare sheltered water surface area.

The south dike has a total length of 606.80 m, with a first section of 202.50 m formed by a sloping wall and a second section of 404.30 m made up of reinforced concrete caissons.

The perimeter dike is made up of reinforced concrete caissons with a total length of 580.60 m.

The southwest dike is made up of reinforced concrete caissons 29 m high, 1,036 m long and with a draft depth ranging between 22 and 50 m.

GENERAL INFORMATION

  • Location: Murcia, Spain.
  • Contract type: Construction.
  • Infrastructure: Construction of a 606.8-m long enclosure dike between Punta de los Aguilones and the Escombreras islet, which surrounds it, a 580.6-m long perimeter dike and a parallel jetty.
  • Year of project completion: 2004