We used necessary cookies for the website to function correctly, guaranteeing basic functionalities and the security of the website. In addition. Depending on your selection, we will use our own and third-party cookies to improve the functioning; preferences cookies, related to the type of browser or the region from which you access, and/or marketing cookies that allow us to analyze browsing habits. For further information, please consult our cookies policy.

You can accept all cookies, configure them or reject their use bellow.

Our foundation: acciona.org Initiatives we support Our strategy Sustainable Development Goals Social development Sustainability indices Sustainable Development Alliances Technology and innovation centres Open and collaborative innovation Digital hub Innovation projects Job offers Graduates and internships Opportunities and inclusion Safety, health and well-being Training Energy Transport Water Social Cities Real Estate Financial Integrated annual report Annual accounts Results, reports & presentations Average period of payment to suppliers Ratings Share price Dividends Analyst opinions Investor calendar General Shareholders' Meeting Board of Directors and Committees Share capital Annual Corporate Governance Report Director remuneration Governance rules and compliance Framework Agreement CNMV Communications Sustainable finance

This project involved the construction of the breakwater and the jetty that make up the new port area on the Mediterranean side.

The project included the construction of a 606.8-m long enclosure dike between Punta de los Aguilones and the Escombreras islet that surrounds it, a 580.6-m long perimeter dike and a jetty parallel to the existing Bastarreche dike, thus creating a 70 hectare sheltered water surface area.

The south dike has a total length of 606.80 m, with a first section of 202.50 m formed by a sloping wall and a second section of 404.30 m made up of reinforced concrete caissons.

The perimeter dike is made up of reinforced concrete caissons with a total length of 580.60 m.

The southwest dike is made up of reinforced concrete caissons 29 m high, 1,036 m long and with a draft depth ranging between 22 and 50 m.

GENERAL INFORMATION

  • Location: Murcia, Spain.
  • Contract type: Construction.
  • Infrastructure: Construction of a 606.8-m long enclosure dike between Punta de los Aguilones and the Escombreras islet, which surrounds it, a 580.6-m long perimeter dike and a parallel jetty.
  • Year of project completion: 2004