650,000

Inhabitants supplied

First project of the Water business in Western Australia

The ACCIONA JV is the delivery contractor for the project and is responsible for the design, construction, operation and maintenance of the A$300M water treatment plant.

The Helena Water consortium, comprising ACCIONA, TRILITY, Brookfields Multiplex, and Royal Bank of Scotland, won the tender to design, build and operate the Mundaring drinking water treatment plant in the Perth area (Western Australia) for a 35 year period.

 

This is a PPP (Public Private Partnership) project in the state of Western Australia. 

The plant supplies the Goldfields and Agricultural Water System (G&AWS), including Kalgoorlie in the state of Western Australia.

Its initial capacity will be 167,000 m3 per day, with a maximum capacity of around 240,000 m3 per day.

Key figures

650,000

inhabitants served

165,000

m3 per day

35

years of D&C and O&M contract

Awards and recognitions

technologies and innovation

Dissolved Air Flotation Filtration (DAFF)

Biological Activated Carbon (BAC)

Discover other projects of ACCIONA