Our foundation: acciona.org Initiatives we support Our strategy Sustainable Development Goals Climate emergency Social development Sustainability indices Sustainable Development Alliances Technology and innovation centres Open and collaborative innovation Digital hub Innovation projects Job offers Graduates and internships Diversity, equity and inclusion Safety, health and well-being Training Selection process Energy Transport Water Social Cities Real Estate Financial Integrated annual reports Annual accounts Results, reports & presentations Average period of payment to suppliers Ratings Share price Dividends Analyst opinions Investor calendar General Shareholders' Meeting Board of Directors and Committees Management team Share capital Annual Corporate Governance Report Director remuneration Governance rules and compliance Framework Agreement CNMV Communications Sustainable finance
Bilbao, Spain See on Google Maps
The extension of Line 2 was carried out over a 920-m section between 2001 and 2004, including the construction of the 108-m long Sestao cavern station below the Gran Vía.

The project was carried out using the NATM (New Austrian Tunnelling Method) conventional tunnelling method, excavating the rock by mechanical means in an urban area with several services and maximized integration in the city.

GENERAL INFORMATION

  • Location: Bilbao, Spain.
  • Contract type: Design and construction.
  • Infrastructure: Extension of Line 2 over a 920-m section, including the construction of the 108-m long Sestao cavern station.
  • Year of project completion: 2004